 ====== THE GUIDED MISSILE FRIGATE (DLG) ANTI-AIR WARFARE MODERNIZATION PROGRAM ====== ====== THE GUIDED MISSILE FRIGATE (DLG) ANTI-AIR WARFARE MODERNIZATION PROGRAM ======
    
-###U. S. General Accounting Office Staff Study - DLG Anti-Air Warfare Modernization Program - Department of the Navy###+###**U. S. General Accounting Office Staff Study - DLG Anti-Air Warfare Modernization Program - Department of the Navy**### 
 ===== PROGRAM DESCRIPTION AND STATUS ===== ===== PROGRAM DESCRIPTION AND STATUS =====
  
-###The DLG Anti-Air Warfare Modernization Program is primarily intended to improve the anti-air warfare capabilities of the 10 ships of the DLG-6 class, the nine ships of the DLG-16 class, and the nuclear DLG(N)-25. Modernization will enable these ships to launch TERRIER and STANDARD missiles from the same launcher. Illustrations of the DLG-6 and DLG-16 class ships are attached as Appendixes I and II. The DLG(N)-25, will have about the same above deck profile as shown tor the DLG-16 class.+###The DLG Anti-Air Warfare Modernization Program is primarily intended to improve the anti-air warfare capabilities of the 10 ships of the DLG-6 class, the nine ships of the DLG-16 class, and the nuclear DLG(N)-25. Modernization will enable these ships to launch TERRIER and STANDARD missiles from the same launcher. Illustrations of the DLG-6 and DLG-16 class ships are attached as Appendixes ​[[aawmod#​APPENDIX ​I|I]] and [[aawmod#​APPENDIX II|II]]. The DLG(N)-25, will have about the same above deck profile as shown tor the DLG-16 class.
  
 All ships are being equipped with an improved three-dimensional air search radar, an improved guided missile fire control system, and the Naval Tactical Data System. Changes are also being made to improve the communications system, increase the anti-submarine detection capability, and to increase the electrical generating and air-conditioning capacities. In addition to modernizing the ships, needed repairs and rehabilitation are being made to ship structures and equipment. All ships are being equipped with an improved three-dimensional air search radar, an improved guided missile fire control system, and the Naval Tactical Data System. Changes are also being made to improve the communications system, increase the anti-submarine detection capability, and to increase the electrical generating and air-conditioning capacities. In addition to modernizing the ships, needed repairs and rehabilitation are being made to ship structures and equipment.
Line 11: Line 12:
  
 The first of the remaining four ships of the DLG-6 class started the program in October 1972 and modernization of all four ships is scheduled for completion by March 1976. The DLG(N)-25 is scheduled to start in June 1974, and be completed in October 1976.### The first of the remaining four ships of the DLG-6 class started the program in October 1972 and modernization of all four ships is scheduled for completion by March 1976. The DLG(N)-25 is scheduled to start in June 1974, and be completed in October 1976.###
 +
 ===== PROGRAM COST EXPERIENCE ===== ===== PROGRAM COST EXPERIENCE =====
  
Line 25: Line 27:
 |Estimating Change | (+) 1.8 | | |Estimating Change | (+) 1.8 | |
 |Other Changes | **__(-) 1.4__** |  **__(+) 14.0__** ​ | |Other Changes | **__(-) 1.4__** |  **__(+) 14.0__** ​ |
-| | | |+||||
 |Program Costs as of June 30, 1972 | |  **__$ 1,​020.6__** ​ | |Program Costs as of June 30, 1972 | |  **__$ 1,​020.6__** ​ |
  
Line 103: Line 105:
  
 The only characteristic change made in fiscal year 1972, will provide increased air search capability to the last four DLG-6 ships to be modernized. This capability will also be given to the DLG(N)-25.###​ The only characteristic change made in fiscal year 1972, will provide increased air search capability to the last four DLG-6 ships to be modernized. This capability will also be given to the DLG(N)-25.###​
- 
 ===== PROGRAM SCHEDULE EXPERIENCE ===== ===== PROGRAM SCHEDULE EXPERIENCE =====
  
-###As of June 30, 1972, the six DLG-6 and three DLG-l6 class ships that had not yet completed the program were expected to do so on or before their scheduled milestone dates. According to a project official, one of the DLG-6 ships may experience a starting delay because its funding was postponed 1 year to fiscal year 1974. Should this occur, there would be a delay in the completion of the ship's modernization. ​+###As of June 30, 1972, the six DLG-6 and three DLG-16 class ships that had not yet completed the program were expected to do so on or before their scheduled milestone dates. According to a project official, one of the DLG-6 ships may experience a starting delay because its funding was postponed 1 year to fiscal year 1974. Should this occur, there would be a delay in the completion of the ship's modernization. ​
  
-We reported in our March 1972 study that the DLG(N)-25 had experienced a l2-month delay in the start of its modernization work. During this review, we noted that the ship start date has been delayed an-additional three-months. This is due to the ship's nuclear engine'​s ability to operate longer than anticipated before replacement.+We reported in our March 1972 study that the DLG(N)-25 had experienced a 12-month delay in the start of its modernization work. During this review, we noted that the ship start date has been delayed an-additional three-months. This is due to the ship's nuclear engine'​s ability to operate longer than anticipated before replacement.
  
 The two DLG-6 ships completing the program in fiscal year 1972, completed the program 3 to 4 months later than expected. The delays were primarily caused by engine auxiliary exhaust problems and high fire room temperatures encountered during final contract trials. These problems were subsequently corrected.###​ The two DLG-6 ships completing the program in fiscal year 1972, completed the program 3 to 4 months later than expected. The delays were primarily caused by engine auxiliary exhaust problems and high fire room temperatures encountered during final contract trials. These problems were subsequently corrected.###​
Line 125: Line 126:
  
 ###A draft of this staff study was reviewed by Navy officials associated with the management of this program and comments were coordinated at the Headquarters level. The Navy's comments are incorporated as appropriate. As far as we know there are no residual differences in fact.### ###A draft of this staff study was reviewed by Navy officials associated with the management of this program and comments were coordinated at the Headquarters level. The Navy's comments are incorporated as appropriate. As far as we know there are no residual differences in fact.###
 +